By: NELSON V. CONSTANTINO, Editor-in-Chief
and CARMELITO Q.
FRANCISCO, Correspondent
with Wire Reports
POWER shortage continued to stall businesses in several provinces
in Mindanao as the National Grid Corporation of the Philippines (NGCP) started
imposing load curtailment in 33 electric cooperatives as power supply has
fallen due to alleged generation deficiency.
NGCP, the private sector operator of the state-owned transmission
grid, is projecting an average shortage of 179 megawatts (MW) for the island
next month to as high as 345 MW in April.
“The curtailment is Mindanao-wide. I don’t know how many cooperatives there are
but everyone is affected. (Power)
reserves are in the negative. We’ve been on Red Alert for several weeks now,”
said NGCP spokesperson Cynthia Perez Alabanza.
Severely affected are the provinces of Maguindanao, North
Cotabato, South Cotabato, and most parts of Sarangani, which are now suffering
power outages lasting one to six hours.
Also affected by the load curtailment are General Santos,
Cotabato, Iligan, Surigao, Kidapawan, and Zamboanga. NGCP corporate communications officer for
Mindanao Milfrance Capulong said only Davao and Cagayan de Oro cities have so
far not been affected by the power outages because of the sufficient resources
of local power firms.
Davao City has a standby power plant, which helps avert blackouts
at this time.
“We impose load curtailment to protect the stability of the
(Mindanao) grid. Let’s say that the grid
is the national highway; everybody taps into the grid. Kung magkaroon ng problema yung grid, walang
makakagamit ng kuryente maski may dumadaloy na kuryente,” Alabanza stressed.
In a power sector forum organized by the Cagayan de Oro Chamber of
Commerce and Industry Foundation, Inc. last week, Eugene H. Bicar, assistant
vice-president for Mindanao systems operations of NGCP, showed that from the
727 MW of installed capacity, the current peak capability of the Agus
hydropower plants is only 467 MW.
The lower output can be traced to several issues, officials said.
Pedro C. Ambos, Jr., National Power Corp. (NAPOCOR)
officer-in-charge for operation and planning, explained in the same forum that
the state power firm could not operate the hydropower plants at maximum
capacity as the discharge of water that will allow such output will flood
low-lying areas in Lanao del Sur province where the plants are located.
Agus 1, for example, is limited to 45 MW from its 80-MW installed
capacity, even as the power needs of the distribution utilities in the last
quarter have outstripped the allocation in their contracts with Napocor, he
said.
Mr. Ambos also admitted that Napocor’s funds for maintenance and
operations have been cut in preparation for the planned privatization of the
power plants.
Construction of infrastructure to protect communities from
possible flooding, he added, is being undertaken by the Department of Public
Works and Highways.
![]() |
| Bicar |
NGCP’s Mr. Bicar, for his part, stated the company’s position that
Mindanao’s power woes are due to generation deficiency and not due to failure
to renew Ancillary Service Procurement Agreement with power barges.
“We could not construct a power plant,” he said.
Meanwhile, the Mindanao Coalition of Power Consumers has sent out
a petition to discontinue the implementation of the Leyte-Mindanao Interconnection
Project of the NGCP.
“We believe that there is no need to carry out the phase 1 work,
despite its approval by the Energy Regulatory Commission, as it is no longer
economically feasible to carry out the main project itself,” the petition
reads.
The coalition noted that the project was deemed feasible in the
mid-’90s when power was considered to be transmitted from the geothermal plants
in Leyte. However, with the present
power requirements in Luzon and the Visayas, the power generated in Leyte would
not be enough to supply Mindanao as well.
In Davao City, customers of the Aboitiz-led Davao Light and Power
Co. will pay an additional P0.2276 per kilowatt-hour (kWh) this month as
Napocor started to impose its so-called dry season rate.
Mindanao’s power supply is heavily dependent on hydroelectric
power.
Rossano C. Luga, company spokesperson, explained that the rate has
been applied since two years ago based on the imposition of the state-run power
company.
Davao Light, however, said the transmission charge based on the
billing from the NGCP will be lower by P0.0665/kWh as a result of lower
ancillary charges. Ancillary charges are
imposed on power consumed from sources that only operate as needed. (BusinessWeekMINDANAO)






0 comments:
Post a Comment